the hardest and most awaited job, work like this is indeed very difficult, but this is what all field officers have been waiting for, installing a transformer set like this is very, very difficult and requires more energy.
this is the last transformer we received yesterday and we have to finish this item today, but we can't activate it right away because the oil or oil is lacking and the stock in the warehouse has run out.
before installing the transformer we first installed a steel frame for the holder, but this was completed a few days ago by another team who served as the initial frame installer such as poles and frames.
What I'm afraid of is that when we were installing this transformer, local people saw us working and it was very dangerous, especially when there were many children passing by.
the cable at this point is also very large and a little hampered when the transformer is raised using a crane, the team must also be limited to being on the pole to avoid unwanted things.
After the transformer was locked on top of the pole, we decided to hire one more worker so that the work would be faster and neater. Even Nikke Ayas was not a random person, he was an average experienced and highly educated person.
after the transformer and other tools are installed and suddenly the boss comes to the field to make sure all the parts are installed correctly, to check the transformer parts it takes quite a bit of time and accuracy, usually this is done by the field leader or foreman.
after everything is done, but this transformer cannot be activated today because the oil is lacking and it is very dangerous if it is forced to activate, so we decided to come back here in a few days, hopefully the oil will come faster so that the electricity line This new one can be activated immediately.