Hi hivers,
What a day, let me flaunt my handwork.
This is a two bedroom apartment which was contracted for interior design finishing. What to be done are:
- Scrapping of the walls & pop
- It will be painted white,
- Installation of 3d panels,
- Installation of window blinds,
- Installation of Viber design
- Installation of picture posh.
Let's take it one after the other:
Scrapping of the walls and pop:
This process is to give it a smooth surface in other for the paint to be able to look smooth on without any rough surface showing on it.
This was scrap for smoothness.
After it has been scrapped, it remains the painting.
Painting of all the whole walls and the pop with Satin White:
Once the walls and the pop are been scrapped, it will now accept paint on it.
White Satin paint was now been applied on the walls and Pop as you can see below. You will be seeing before and after
After the painting of the whole building to satisfaction. We proceed.
Installation of the 3 d panels
The installation is done systematically with carefulness and patient because of straightness.
Materials are:
- 3d panel
- Hammer (Soft) 'depending'
- Tape
- Gum
- Brush or Spraying Machine
- Paint
Process: Try to get the first square of the walls to install the panel
Getting the first square of the wall is the main work,once it is done, the work has reduced
Installation continued
Painting of the 3d panel commence immediately after installation to give it a finer and beautiful finishing
Installation of the Viber for beautification
Work continues....